Which activities are covered in the project "go-live" during the Transition phase?

Boost your SAP S/4HANA Cloud skills. Master the Private Edition Implementation with SAP Activate with detailed questions, hints, and explanations. Prepare effectively for your certification test!

The "go-live" phase of a project, particularly within the Transition phase of the SAP Activate methodology, focuses on activities that ensure a successful launch of the new system in a real environment. During this crucial time, cutover planning is a key activity where the final details are worked out to ensure a smooth transition from the old system to the new SAP S/4HANA Cloud system. This involves meticulous planning of how business operations will switch over, including the timing and sequence of tasks required to facilitate this transition.

End-user training is another critical component of this phase as it equips users with the skills and knowledge necessary to effectively operate the new system. Ensuring that users are well-prepared is vital for user adoption and for leveraging the capabilities of the new system right from the start. Without proper training, even the best systems can face challenges in usability and acceptance.

Therefore, the selection of cutover planning and end-user training is correct as these activities are pivotal in the lead-up to going live, ensuring both technical readiness and user competency.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy